General Electric Combined Cycle Power Plant Cap. 125 MW

General Electric Combined Cycle Power Plant Cap. 125 MW

Category:

Description

General Electric Combined Cycle Power Plant Cap. 125 MW

BRAND : GENERAL ELECTRIC

TECHNICAL DETAIL

The Power Plant’s total installed power is 125 MWh, total yearly production  capacity is 1.033 GWh.
GE LM6000 PC Sprint Power Plant :

 

S/N : 191539 LM6000PC Sprint CNG + Liquid (Naphtha)
– Manufactured Date 2004
– Running Hours 50900
– Over-haul 13.04.2012
– After Over-haul Running Hours 11140
S/N: 191648 LM6000PC Sprint CNG
– Manufacturer Date 2010
– Running Hours 17785
SIEMENS Steam Turbine (1 x 27.3 mwh)
– Manufactured Date 2001
– Running Hours 86,150
– Over-haul 01.07.2013
– After Over-haul Running Hours 6455

 

Air Cooled Condenser System
– Steam coming from the steam turbine condensed and collected in condensate tank and sent to the boiler back.